Crematory Installation

Prior to arrival of your crematory, FC Industries will consult with your gas utility, plumber, electrician & roofer. Our goal is to ensure a smooth installation.
Factory trained personnel manage all phases of crematory / incinerator installation including:

  1. Assist crane and rigging company with offloading and setting of cremation unit
  2. Oversee setting of stack sections
  3. Supervise final connection of gas and electric utilities
  4. Start up and fine tuning of controls
  5. Curing of refractory
  6. Conducting a test burn